PMJM 330 Colorado State Univ Calculating Budgeted Cost of Work Performed Excel Task

PMJM 330 Colorado State Univ Calculating Budgeted Cost of Work Performed Excel Task

Description

 

 

Don't use plagiarized sources. Get Your Custom Essay on
PMJM 330 Colorado State Univ Calculating Budgeted Cost of Work Performed Excel Task
Just from $13/Page
Order Essay

Download and read the Module 4 Critical Thinking Assignment (Option 2) file in this module, and in the document, complete the highlighted sections as directed. Refer to Chapter 14 from the Project Management text and Part 1, Chapter 7 from the PMBOK® Guide for directions on how to calculate these financials. Follow the CSU Global Writing Center (Links to an external site.) for how you will be graded on the essay question writing portions of the assignment.

ORDER A PLAGIARISM FREE PAPER NOW

Module 4 Critical Thinking Assignment (Option 2):

Option 2: Calculating BCWP (EV)

You are the sponsor for project XY. The project manager has provided you the following three status reports. The project started in Week 1 and it is now the end of the 4th week. PMJM 330 Colorado State Univ Calculating Budgeted Cost of Work Performed Excel Task

For this assignment, complete this packet in its entirety to include all tables, blanks, and questions. Complete the file and submit as your completed assignment.

Project Planning Budget: Dollars Budgeted Per Week for Each Activity

Activity Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Total $
AB 2,000 2,000 2,000 6,000
AC 3,000 4,000 4,000 4,000 5,000 20,000
AD 2,000 3,000 2,500 7,500
BF 2,000 3,000 4,000 3,000 3,000 15,000
CE 2,500 2,500
DE 3,500 3,500 3,500 10,500
EF 3,000 3,000
Total: 7,000 9,000 8,500 9,500 11,500 10,000 6,000 3,000 64,500

Percent Completion Report: End of Week 4

Activity Date Started Percent completed Time to Complete (weeks)
AB Week 1 100 Completed
AC Week 2 (Approved delay,
1 week)
40 3
AD Week 1 100 Completed
BF Week 4 40 3
DE Not started—unapproved delay 0 2

Cost Summary

  Week 4 Cumulative to Date
Activity Budget Cost Actual (Over) / Under Budget Cost Actual (Over) / Under
AB 6,000 6,200 (200)
AC 4,000 4,500 (500) 11,000 9,000 2,500
AD 2,400 (2,400) 7500 7,400 100
BF 2,000 2,800 (800) 2,000 4,500 (2,500)
DE 3,500 3,500 3500 0 3,500
Total 9,500 9,700 (200) 34,000 30,600 3,400

It is now the end of Week 4 and you want to determine the status of the project using earned value management. Complete the table and earned value metrics below. Some of the information has already been entered for you. PMJM 330 Colorado State Univ Calculating Budgeted Cost of Work Performed Excel Task

Activity % Complete Planned Value (PV) Earned Value (EV) Actual Cost (AC) Cost Variance Schedule Variance Total Budget
AB 6,200 6,000
AC* 40 8,000 20,000
AD 7,500
BF 6,000 15,000
CE n/a 2,500
DE* 0 10,500
EF n/a 3,000
TOTAL 64,500
* Note that activity AC was delayed one week (approved) and its planned value has been adjusted.
* Activity DE is one week behind schedule (not approved), so its original planned value is still included.
Calculate each of the following:
Cost Variance ($) = EV – AC
Schedule Variance ($) = EV – PV
Schedule Variance (weeks) = Schedule Variance ($) / Average Weekly PV
Cost-at-Completion = (Rate of Spending x Total Budget) = ([AC / EV] * Total Budget)
CPI = EV / AC
SPI = EV / PV

Add your written analysis below by answering three questions:

 

  • What is the state of the project?
  • Which activity has had the most positive impact on the project?
  • Which activity has had the most negative impact on the project? PMJM 330 Colorado State Univ Calculating Budgeted Cost of Work Performed Excel Task